Our first large Client has been ORION Energy in Ecuador, Operator of the ENO-RON and OCANO-PEÑA BLANCA fields providing services of:

Bidding Terms for the fourth Drilling campaign (September 2017-December 2017).

Servicios de Ingeniería de Perforación/Completación en diferentes posiciones de supervisión (Enero 2018 – Agosto 2018, 4 pozos perforados).

Drilling Fluid Design Services for the Fourth Drilling Campaign of ORION Energy (September 2017 – December 2017).

Servicio de Reacondicionamiento de pozos con Ingeniería, Servicios y Supervisión en campo (Enero 2019)

Drilling / Completion Engineering Services in different supervisory positions (January 2019 – March 2019).

Integrated Drilling/Completion Service of a re-entry in RON, providing all the services for the execution of the May 2019 project.

Achievements

Faster directional well of all Drilling campaigns, planned in 23 days and executed in 17 days, reducing the cost per foot by 30usd/day compared to the fastest well as previous reference and allowing it to produce 6 days earlier than expected.

Achievements

Faster directional well of all Drilling campaigns, planned in 23 days and executed in 17 days, reducing the cost per foot by 30usd/day compared to the fastest well as previous reference and allowing it to produce 6 days earlier than expected.

Testimonials

“We chose Drillcotec, above all, for its closeness to us, its client, when aligning itself with our needs. As Orion we were not only able to transfer the execution risks to Drillcotec, as an expert supplier, but also, we received innovative alternatives that allowed us to generate security and efficiency for the benefit of both parties.

The results, without a doubt, were beyond our expectations. Not only managing to overcome complexities during execution in an agile and safe way; but also, achieving material improvements in time and our historical costs per foot drilled”.

¿Would you recommend working with Drillcotec?

Definitely! I consider it to be the ideal combination of experienced and committed talent, with a “boutique” structure that generates closeness and trust in the client”.

Fernando Emanuele
CEO Orion Energy Ecuador

CUYABENO PETRO

A second important client of us is CuyabenoPetro, with a service contract for the development of Cuyabeno Sansahuari fields, providing services of:

More than 37 wells drilled according to plan to date.

Design of the drilling and engineering plan

Provision of all services for drilling and disposal of drilling fluids and gravel

  • CYBC-074 directional well, planned in 13 days and executed in 10.25 days. This well obtained the highest production in the field at the time.
  • CYBC-090 directional well, planned in 9.5 days and executed in 7.33 days (Current record in the entire Cuyabeno field).

Integrated Completion Services

Achievements

CYBC-074 directional well, planned in 13 days and executed in 10.25 days. This well obtained the highest production in the field at the time.

CYBC-090 directional well, planned in 9.5 days and executed in 7.33 days (Current record in the entire Cuyabeno field).

Achievements

CYBC-074 directional well, planned in 13 days and executed in 10.25 days. This well obtained the highest production in the field at the time.

CYBC-090 directional well, planned in 9.5 days and executed in 7.33 days (Current record in the entire Cuyabeno field).

More Achievements

The Key Performance Indicator (KPI) of effectiveness in drilling operations is the feet/day achieved, where Drillcotec, in several assigned drilled wells, has the best KPI with approximately 40% less cost.

More Achievements

The Key Performance Indicator (KPI) of effectiveness in drilling operations is the feet/day achieved, where Drillcotec, in several assigned drilled wells, has the best KPI with approximately 40% less cost.

FRONTERA ENERGY

In November 2021 we won the bidding process to provide the Supervision Service during the drilling of three wells in the Perico Block, in the Amazonian province of Sucumbíos.

We Create Engineering Solutions